November marked another busy month for the team on the ground at The Reserve, with construction progressing smoothly as we approach the end of the year.

In Stages 1 and 2, we’re thrilled to share that Council Practical Completion has been achieved! Currently we are working through the final authority audits and expect to achieve Statements of Compliance shortly.

In Stage 3, sewer works are now complete, with drainage reticulation currently underway, while in Stage 4 the sewer works are progressing well on the way to completion.

We’re pleased to share that earthworks have now commenced in Stage 5, marking an exciting milestone for this Stage!

From the Sales Office, the final lots in Stage 6 are selling quickly, so reach out to our friendly sales team today if you’re interested in securing your slice of The Reserve in Armstrong Creek!

For more information on available lots or future releases at The Reserve, you can contact our sales team on 0428 834 374 or email [email protected].

View Construction Updates Page

View Available Properties

Register Your Interest General - Updated (2024)

By continuing you are agreeing to the Privacy Policy and Disclaimer.

Marketing opt-in
Close
Register