We’re proud to report that the construction of The Reserve has commenced!
To keep up to date on its progress, register your interest to have updates sent straight to your inbox.

In progress:

Stage 1

Titles estimated: September 2022

View Details

61%

Planning100%


Planning100%


Civil Construction62%


Site Establishment100%


Bulk Earthworks100%


Drainage Works100%


Sewer Works100%


Water & Gas Reticulation100%


Subgrade Placement Works60%


Electrical & NBN0%


Footpaths/Asphalt/Linemarking0%


Practical Completion0%


Registration Progress0%


Statement of Compliance0%


Lodge Plan of Subdivision0%


Titles0%


Close Details

Stage 2

Titles estimated: September 2022

View Details

61%

Planning100%


Planning100%


Civil Construction62%


Site Establishment100%


Bulk Earthworks100%


Drainage Works100%


Sewer Works100%


Water & Gas Reticulation100%


Subgrade Placement Works60%


Electrical & NBN0%


Footpaths/Asphalt/Linemarking0%


Practical Completion0%


Registration Progress0%


Statement of Compliance0%


Lodge Plan of Subdivision0%


Titles0%


Close Details

Stage 3

Titles estimated: Q2 2023

View Details

9%

Planning100%


Planning100%


Civil Construction4%


Site Establishment40%


Bulk Earthworks0%


Drainage Works0%


Sewer Works0%


Water & Gas Reticulation0%


Subgrade Placement Works0%


Electrical & NBN0%


Footpaths/Asphalt/Linemarking0%


Practical Completion0%


Registration Progress0%


Statement of Compliance0%


Lodge Plan of Subdivision0%


Titles0%


Close Details

Stage 4

Titles estimated: Q2 2023

View Details

3%

Planning60%


Planning60%


Civil Construction0%


Site Establishment0%


Bulk Earthworks0%


Drainage Works0%


Sewer Works0%


Water & Gas Reticulation0%


Subgrade Placement Works0%


Electrical & NBN0%


Footpaths/Asphalt/Linemarking0%


Practical Completion0%


Registration Progress0%


Statement of Compliance0%


Lodge Plan of Subdivision0%


Titles0%


Close Details

Stage 5

Titles estimated: Q2 2023

View Details

1%

Planning20%


Planning20%


Civil Construction0%


Site Establishment0%


Bulk Earthworks0%


Drainage Works0%


Sewer Works0%


Water & Gas Reticulation0%


Subgrade Placement Works0%


Electrical & NBN0%


Footpaths/Asphalt/Linemarking0%


Practical Completion0%


Registration Progress0%


Statement of Compliance0%


Lodge Plan of Subdivision0%


Titles0%


Close Details

Stage 6

Titles estimated: Q3 2023

View Details

1%

Planning10%


Planning10%


Civil Construction0%


Site Establishment0%


Bulk Earthworks0%


Drainage Works0%


Sewer Works0%


Water & Gas Reticulation0%


Subgrade Placement Works0%


Electrical & NBN0%


Footpaths/Asphalt/Linemarking0%


Practical Completion0%


Registration Progress0%


Statement of Compliance0%


Lodge Plan of Subdivision0%


Titles0%


Close Details

* Estimated title dates are provided as an approximate guide only and are subject to change.

The title date estimates provided are based on current information regarding the design, construction, and relevant authority approvals timeframes for the individual stage. The Reserve uses this information to provide an estimate of the month (or month/quarter ranges) in which titles will be achieved however this is subject to change and is often influenced by factors which are often outside of the projects control such as weather, contractor delays and authority inspections.